Beth Israel Deaconess Hospital - Milton - 2 North

Acute Care
2 North
Adult Medical / Surgical Combined
Variance Info
Current Posted Planned Worked Hours Per Patient Day 7.46
Actual Worked Hours Per Patient Day 7.02
Variance -0.44
% Variance from Budget -5.90%
 
Reason For +/- 5% Variance From Budget
No explanation required  
Fluctuating day to day census  
Lower daily census than planned  
Higher daily census than planned X
Higher patient care needs than planned X
Lower patient care needs than planned  
Staff vacancies X
Adjusted for patient care needs  
Minimum fixed staffing requirements  
Care delivery model changes  
Increased 1:1 staffing requirements X
Closure of unit  
Not admitting to beds due to staffing  
Increased census to telemetry patients X
Plan based on high needs in critical care  
Increased staff hours to facilitate admissions and discharges  
Change in patient mix X
 
Other Reasons for +/- 5% Variance
Unexpected closure of Steward Quincy medical Center (December 2014) resulted in higher than budgeted inpatient volumes for the hospital. Strategies implemented to increase nursing recruitment/retention/remuneration to attain budgeted NHPPD.
 
Additional Comments

« Back